Bridgeland Main Street: Streetscape and Infrastructure Work on 1 Avenue NE
In support of the City of Calgary’s Bridgeland Main Street Project, TELUS infrastructure work will take place along 1 Avenue N.E. between 4 Street and 6 Street N.E. The work will be completed by BRT Construction..
Scheduled Work Dates and Locations
September 15–19, 2025: Closure of westbound vehicle lanes from Edmonton Trail N.E. to 6 Street N.E.
September 22–26, 2025: Closure of westbound vehicle lanes from 4 Street N.E. to Edmonton Trail N.E.
Work will occur daily between 7:00 a.m. and 10:00 p.m. Lane closures will remain in place 24/7 during each setup period due to open excavation.
What to Expect
Westbound lane closures in effect, impacting street parking.
Two-way traffic maintained throughout construction along the existing eastbound lanes.
Each setup will last approximately one week per block, depending on weather and underground conditions.
Sidewalk and driveway access will remain open during construction.
Businesses may experience noise and construction activity during working hours.
Next Steps
This work marks another stage of streetscape and infrastructure improvements in Bridgeland. The project team will continue to share updates and keep the community informed as construction progresses.