Green Line Ground Investigations
Beginning in mid-April, a series of borehole tests will take place to analyze ground conditions along the Green Line alignment. Work will occur on City-owned property and no significant impacts are expected on roadways. Each test will take one to two days. If more direct impacts are expected to residents or businesses, the Green Line team will coordinate directly with those affected.
Following this series of borehole tests, additional locations along the alignment will be investigated in July and August.
Dates + Locations:
114 Ave/Barlow Tr SE – April to June
Ogden – Early May
Highfield/Blackfoot Trail – Mid to late May
Ramsay – Late April and June
For more detailed information and maps of approximate investigation sites, visit Calgary.ca/GreenLine/CurrentConstruction